This is the eighth, and nearly last, post in the series on T&L reconstruction. In the previous post, I covered the construction of the building's skeleton.
In this post, we'll be looking at the filling in of the walls and ceilings.
In mid-December, the snow started falling, so the roof installation and wall framing were timely.
A week later, the metal roof was finished and they had started to install the fibreglass wallboard, which comes in yellow packaging.
A few days later, this machine was pumping tar up to the roof for the finishing weather sealant. Much of the walls are still open, so we can see right into and through the building.
The artistic bike racks along Bank Street were wrapped in packing material to protect them during the ongoing construction. Behind, the windows along Bank Street have been installed.
On this shot from Christmas Eve, the fibreglass sheathing was formed around the front entrance at the corner, and the "Open Winter 09-10" sign was attached to it.
Meanwhile, scaffolding was beginning to go up around the building for the installation of the second-floor walls. The framing for the McLeod side windows was progressing since the photo above. In the background is the sales centre for the Central Phase II condos.
Around the back side of the building, a blue treatment was applied to the fibreglass sheathing, then some insulation on top of that. The scaffolding is being wrapped in plastic for weather protection.
The rear parking lot is normally full of construction workers' vehicles, but they're away on holidays today.
By mid-January, most of the blue banners advertising the reopening of Bank Street had started to fall down, as with this one bearing the words "Better than ever!" The plastic wrap on the T&L building had extended to the second floor, and some wooden makeshift doors had been installed at the corner.
A pallette of bricks was nearly empty and poking out from the foot of the tarp. Notice the double-high black bricks. Some large propane canisters were helping to provide heat to the bubble.
More bricks and propane tanks were on hand in the overflow parking lot across McLeod from T&L.
The two-storey scaffolding got to the corner of the building by the end of January 2010, and the plastic wrap was enshrouding the Bank Street side as well, including most of a recently-planted tree. A second set of modu-loc fencing created a protective sidewalk space for pedestrians.
In the next post, the bricks go on and the shroud comes off for the big reveal.
No comments:
Post a Comment